BH-Gas maintenance plan in 2023, which affect or could affect the transmission/delivery/acceptance of gas
MONTH | WORK PERFORMANCE LOCATION | IMPACT OF THE WORKS ON TRANSMISSION | DURATION OF WORKS
(h) |
AVAILABLE CAPACITY
(%) |
ACTIVITY |
JANUARY | – no maintenance work is planned for the gas transmission system that affects or could affect the transmission /delivery/acceptance of gas. | ||||
FEBRUARY | – no maintenance work is planned for the gas transmission system that affects or could affect the transmission /delivery/acceptance of gas. | ||||
MARCH | – no maintenance work is planned for the gas transmission system that affects or could affect the transmission /delivery/acceptance of gas. | ||||
APRIL | Main gas pipeline DN 400 Kladanj-Butila, Semizovac Zenica | BS and MRS on the main gas pipeline | 7×24 | 100 | Structural strengthening of defects on gas pipelines after the analysis of the in-line inspection of the gaspipeline |
MAY | MS Semizovac | MRS Misoča
MRS Visoko and Radinovići MRS Kakanj MRS Mittal |
24 | 0
50 50 50 |
Repair, replacement of insulating joints, installation of monobloc |
DN 400 Semizovac-Zenica | BS and MRS on the main gas pipeline | 10×24 | 0-100* | Construction and mechanical works – manhole inspection of gas pipelines, replacement of gas pipeline sections, structural strengthening of defects on gas pipelines after the analysis of the in-line inspection the gas pipeline | |
JUNE | DN 400 (Prijevor-Podpaklenik; Podpaklenik-Butila;) | BS and MRS on the main gas pipeline | 10×24 | 0-100* | Construction and mechanical works – manhole inspection of gas pipelines, replacement of gas pipeline sections, structural strengthening of defects on gas pipelines after the analysis of the in-line inspection of the gas pipeline |
JULY | DN 400 (Prijevor-Podpaklenik; Podpaklenik-Butila;) | BS and MRS on the main gas pipeline | 10×24 | 0-100* | Construction and mechanical works – manhole inspection of gas pipelines, replacement of gas pipeline sections, structural strengthening of defects on gas pipelines after the analysis of the in-line inspection of the gas pipeline |
MRS Kakanj | MRS Kakanj | 48 | 0 | Procurement with installation of a set of two-line pressure regulation at MRS Kakanj. | |
AUGUST | DN 400 Semizovac-Zenica | BS and MRS on the main gas pipeline | 10×24 | 0-100* | Construction and mechanical works – manhole inspection of gas pipelines, replacement of gas pipeline sections, structural strengthening of defects on gas pipelines after the analysis of the in-line inspection of the gas pipeline |
SEPTEMBER | Podklenik-Butila | BS and MRS on the main gas pipeline | 8 | 100 | Internal gas pipeline cleaning |
DN 400 Semizovac-Zenica | BS and MRS on the main gas pipeline | 5×24 | 0-100* | Construction and mechanical works – manhole inspection of gas pipelines | |
OCTOBER | Semizovac-Zenica | BS and MRS on the main gas pipeline | 24 | 100 | Internal gas pipeline cleaning |
NOVEMBER | – no maintenance work is planned for the gas transmission system that affects or could affect the transmission /delivery/acceptance of gas. | ||||
DECEMBER | – no maintenance work is planned for the gas transmission system that affects or could affect the transmission /delivery/acceptance of gas. |
*Depending on the type of inspection results and the required activities after the manhole inspection
NOTE: The annual transmission system maintenance plan refers to planned maintenance activities, so the specified dates for carrying out activities are approximate. The planned date of performance of activities and the duration of outages and/or limitations will be announced 30 days before the planned activities.